Telangana, IndiaHyderabad pathway
- Currency
- INR (₹)
- Published
- 11 August 2026
- Confidence
- Low
- Estimate class
- Early order-of-magnitude sensitivity; independent Telangana cost planning required
- Price basis
- CPWD PAR base 1 April 2025, checked against Correction Slip No 1 and the April 2026 Delhi index; no index rebasing.
Calculated Phase 1 sensitivity₹94.9 to ₹216 croreCalculated pre-feasibility sensitivity, not a published source figure or approved development cost.80,000 to 120,000 sq ft whole-building scientific node, treated as plinth-area-equivalent for the Hyderabad sensitivity, with a CPWD hospital base-rate anchor, disclosed 1.5x to 2.2x laboratory-intensity factor, equipment allowances, shared on-site utilities, fees, commissioning and 25% scenario risk.
Calculation inputsLow case uses every low input; high case uses every high input
- Working GIA / plinth-area-equivalent area
- 80,000 to 1,20,000 sq ft
- Base rate
- ₹2,972 to ₹2,972 per sq ft
- Specialist multiplier
- 1.50x to 2.20x
- Equipment schedule
- ₹25 to ₹60 crore
- Site and utilities
- 15% of core build
- Fees and commissioning
- 15% of core + equipment + enabling
- Risk method
- 25% of the complete pre-risk subtotal
Equipment basisScenario allowances awaiting vendor schedule and quotes
Formulation, analytical and quality systems
Core formulation suites, chromatography, spectroscopy, stability and quality-control systems.
VARUNÉ scenario allowance; local and imported vendor schedule pending. ₹10 to ₹25 croreAutomation, robotics and governed data
Laboratory automation, robotics cells, simulation, secure compute, monitoring and data infrastructure.
VARUNÉ scenario allowance; architecture, duties and vendor quotes pending. ₹7 to ₹18 croreShared controlled environments and cold chain
Selected environmental control, sample management, cold storage and shared technical infrastructure.
VARUNÉ scenario allowance; cleanroom classification and qualification scope pending. ₹8 to ₹17 crore
Formula output by categoryDerived from the disclosed inputs above
- 01
Core building and lab-ready services
Working floor area multiplied by the disclosed base rate and laboratory-intensity factor.
area x base rate x specialist multiplier ₹35.7 to ₹78.5 crore - 02
Scientific, automation and digital equipment
The disclosed equipment schedule summed without a vendor-quote premium.
sum of three equipment allowances ₹25 to ₹60 crore - 03
Site, shared utilities and resilience
On-site services, access, resilience and landscape planning allowance.
15% x core build ₹5.3 to ₹11.8 crore - 04
Design, statutory, commissioning and qualification
Professional, statutory, technical assurance, commissioning and qualification allowance.
15% x (core + equipment + enabling) ₹9.9 to ₹22.5 crore - 05
Unresolved scope, programme and price risk
A visible scenario risk allowance, not a quantified risk analysis or confidence percentile.
25% x complete pre-risk subtotal ₹19 to ₹43.2 crore
Later Hyderabad campus modulesNot quantified
No expanded or full-campus total is published until modules, cleanroom classes, production strategy, equipment ownership, utility loads and development sequence are defined.
- expanded R&D and stability capability
- pilot and technology-transfer modules
- separately governed future manufacturing options
Calculation assumptions, benchmark ledger and exclusions
Assumptions
- No site is selected or controlled; ground, utility, planning, remediation and off-site reinforcement conditions remain unknown.
- The 80,000 to 120,000 sq ft area range is a whole-building GIA-equivalent test-fit input. For Hyderabad planning it is treated as plinth-area-equivalent; it is not net usable or laboratory-only area, no net-to-gross conversion is applied, and it is not a measured design or approved brief.
- No cross-currency conversion or purchasing-power comparison is used.
- The percentage allowances are transparent VARUNÉ planning assumptions pending an independent cost plan; they are not market quotes.
- The 25% risk allowance is applied to the complete pre-risk subtotal. It is not a Monte Carlo model, quantified risk analysis, P50 or P80 confidence level.
- The CPWD hospital rate is a Delhi-base public-sector anchor, not a Hyderabad laboratory quote.
- Correction Slip No 1 changes Annexure II general-specification item 2.1 only; it does not amend rate-table item 1.1.1 or the hospital anchor used here.
- The 1.5x to 2.2x specialist multiplier is an explicit sensitivity for higher services intensity, laboratory finishes and unresolved Delhi-to-Hyderabad differences; it is not a measured location factor.
- The April 2026 Delhi Building Cost Index of 101 is deliberately excluded under the no-index-rebasing method and is not treated as a Hyderabad location factor.
- Telangana SSR 2026-27 must be applied to measured quantities by a local cost professional before a development decision.
Exclusions
- Land purchase or lease premiums; VAT, GST, customs duties, labour cess and tax recoverability.
- Financing, interest, foreign-exchange hedging, working capital, operating losses and ongoing payroll.
- Product development, preclinical or clinical programmes and programme-specific scientific spend.
- Extraordinary off-site grid, water or effluent reinforcement and unknown ground remediation.
- Commercial sterile, biologics, beta-lactam or high-containment manufacturing modules.
- Equipment consumables, service contracts, validation batches, replacement capital and vendor price escalation.
Comparator and normalization ledger
CPWD hospital base rate
- Published evidence
- ₹31,990 per m2
- Derived evidence
- ₹2971.97 per sq ft before multiplier
- Price basis
- PAR base 1 April 2025; item 1.1.1 RCC framed hospital, up to six storeys
- Normalization
- Correction Slip No 1 was checked and does not amend item 1.1.1. No escalation or Hyderabad index is applied. A visible 1.5x to 2.2x planning factor tests laboratory intensity and unresolved location/specification differences.
- Formula use
- Single base-rate anchor x disclosed specialist multiplier
CPWD Delhi cost index April 2026
- Published evidence
- Delhi index 101 at 1 April 2026; PAR 1 April 2025 base 100
- Derived evidence
- No index factor applied
- Price basis
- Reference 68/SE(TAS)/CI/2026/99-H
- Normalization
- Deliberately excluded under no index rebasing; a Delhi index is not a measured Hyderabad location factor.
- Formula use
- Market context only - excluded from formula
Gleeds India Q3/Q4 FY26
- Published evidence
- Current market-report release dated 30 October 2025
- Derived evidence
- No Gleeds rate inserted
- Price basis
- Q3/Q4 FY26 market context
- Normalization
- No factor derived from narrative market commentary.
- Formula use
- Market context only - excluded from formula
Telangana SSR 2026-27
- Published evidence
- Current state item-rate schedule
- Derived evidence
- No whole-building rate derived
- Price basis
- 2026-27 schedule listed first at source cut-off
- Normalization
- Reserved for a measured local bill of quantities, not collapsed into an invented area rate.
- Formula use
- Local validation source - excluded from formula
Source-to-category register
Plinth Area Rates 2025Base date 1 April 2025; item 1.1.1 hospital RCC framed structure up to six storeys at ₹31,990/m2. Converted to ₹2,971.97/sq ft before the disclosed laboratory-intensity multiplier.
formula anchor · Central Public Works Department, Government of India · published 2025-07-31 · accessed 2026-08-11
Applies to: Core building and lab-ready servicesCorrection Slip No 1 of Plinth Area Rates 2025Reference 62/SE(TAS)/PAR/2025/15-H, dated 15 January 2026. The one-page slip changes only Annexure II general-specification item 2.1 by clarifying that rates on pages 3 to 11 use RCC framed structures; it does not amend rate-table item 1.1.1 or the ₹31,990/m2 hospital rate.
market context · Central Public Works Department, Government of India · published 2026-01-15 · accessed 2026-08-11
Applies to: Core building and lab-ready services- market context · Central Public Works Department, Government of India · published 2026-04-27 · accessed 2026-08-11
Applies to: Core building and lab-ready services, Unresolved scope, programme and price risk - market context · Gleeds · published 2025-10-30 · accessed 2026-08-11
Applies to: Core building and lab-ready services, Site, shared utilities and resilience, Unresolved scope, programme and price risk Schedule of Rates 2026-27The current state page lists SSR 2026-27 first. It is an item-level local ratebook for the next measured estimate, not a whole-laboratory ₹/sq ft comparator.
local ratebook · Panchayat Raj Engineering Department, Government of Telangana · accessed 2026-08-11
Applies to: Core building and lab-ready services, Site, shared utilities and resilienceNew Rules of Measurement 1Used only to keep early cost categories explicit; local professional measurement and procurement rules must replace it for a Hyderabad cost plan.
method · Royal Institution of Chartered Surveyors · published 2022-10-01 · accessed 2026-08-11
Applies to: Design, statutory, commissioning and qualification, Site, shared utilities and resilience, Core building and lab-ready services, Scientific, automation and digital equipment, Unresolved scope, programme and price risk